Utility Commission Lets Approval of Oncor’s 765-Kilovolt Power Lines Stand
The Public Utility Commission of Texas left rehearing motions on Oncor's two 765-kV lines off its agenda, letting the August approvals become final. Challengers' next step is a Travis County district court.

The Public Utility Commission of Texas will not reconsider its approval of two Oncor 765-kilovolt transmission lines that together would run about 424 miles from Somervell County to Culberson County, according to memos the agency filed November 12.
In each case, “The Commission voted to not add the motion for rehearing of the Commission’s Order” to “any open meeting agenda,” the memos say. Each lists the parties whose motions it set aside. Neither memo carries a signature or a vote count.
The commission approved both lines on August 28. In October it took the longest time the law allows to decide whether to reopen them, as the Texian Partisan reported. Under the Texas Administrative Procedure Act, a rehearing motion the agency does not act on is overruled by operation of law, and the agency cannot extend its time past the 100th day after the order. Once the motions are overruled, anyone challenging the orders has 30 days to file in a Travis County district court.
The eastern line, from the Dinosaur switch near Glen Rose to the Longshore switch near Forsan in Howard County, is 242.56 miles long and crosses 22 counties. Its estimated cost is about $2.24 billion, and Oncor told the commission it would be energized by June 2029. The western line, from Longshore to the Drill Hole switch in Culberson County, runs about 181.6 miles through 10 counties at an estimated $1.70 billion, with a target of December 2028.
The two lines are the western end of what the orders call Import Path 1, part of the Permian Basin Reliability Plan. In approving them, the commission found that electricity demand “driven by oil and gas development in the Permian Basin was expected to continue growing over the next 15 years.” Utilities also projected new load from “cryptocurrency mining operations, data centers, and hydrogen electrolysis facilities.”
The challengers came at the orders from different directions. American Stewards of Liberty, a property rights group, argued that the order “commits a fundamental legal error by treating approval of the Permian Basin Reliability Plan” and ERCOT’s recommendation as enough to prove these specific lines were needed. The Middle Trinity Groundwater Conservation District objected to the commission striking groundwater protections that the administrative law judges had recommended. Two pipeline companies, Delaware Basin Midstream and Brazos Midstream, asked for conditions on electrical interference with the metal pipelines the line will cross.
Oncor answered that “The Commission should deny each motion for rehearing in its entirety.”
The commission did not have to deny anything. It left the motions off its agenda and let the statute’s clock close them. For the landowners along 424 miles of right of way, the next place to argue is a Travis County courtroom.
See more of the Partisan in Google’s Top Stories.Add as a Preferred Source on Google
Read Next
SpaceX Catches Starship’s Upper Stage at Starbase Tower for First Time
SpaceX caught Starship's upper stage with the launch tower at Starbase on Saturday, a first. The Super Heavy booster diverted to the Gulf after its boostback burn ended early.